Under the Critical material tab at the bottom of the Result tab, you will see a total of all critical material. A critical material is a material with maximum difference in days in the range of orders. The Diff column is shown in bold font for critical material in the structure list.
Material is shown with a yellow symbol for P-parts and a green symbol for S-parts. You can see the material's part number, name, number of delays (caused by the material), current supplier with supplier number and name.
You can expand a material to see the manufacturing orders where the material has caused a delay. You can then see the manufacturing order number, part number (the order's main part), period when the material requirement occurs, new arrival period, difference, quantity, unit and order number.
The Critical material tab.