You are here: Manufacturing > Reporting > Operation Reporting > Rest Quantity

Rest Quantity

This field shows the rest quantity that is left. The Rest quantity is the difference between Planned quantity and Reported quantity. If you want to delete the rest quantity, enter a 0 in this field. When deleting rest quantities, the loading for that operation will be recalculated. The system will also adjust the planned quantity for all the following operations, to the quantity that was reported as finished for that operation. If you have checked the option Delete rest material, the system will also delete the material reservations for the quantity that was deleted. Otherwise they will remain.

The system checks if the loaded report number has a rest balance of zero, in which case a red text appears at the bottom of the window indicating that this report number could be reported as finished.

Warning when a report number has a rest balance of zero.