Period
When using the Delivery reliability list, you can under the Period heading select delivery period on the order row with which you want to compare the actual delivery period. The following alternatives are available:
- Current delivery period - delivery reliability is calculated by comparing the actual delivery period and the delivery period that was confirmed by the supplier.
- Initial delivery period - delivery reliability is calculated by comparing the actual delivery period and the delivery period that was initially registered on the order row.
- Requested delivery period - delivery reliability is calculated by comparing the actual delivery period and the delivery period that was initially requested on the order row.