Show Operations

Here you can select which operations that shall be included in the structure list based on different criterias.

Show operations.

All Operations

The value 161 before All operations in the example above, shows the number of operations for which a new finish period has been calculated. The value is the total of delayed and not delayed operations. The value (236) shows the total number of operations in the selected range of orders. The value also includes subcontracts and operations in the work centers for which the setting Reliable new finish has not been configured.

Critical

The value 14 before Critical shows the number of critical operations for the selected order, that is the operations with maximum difference in days for operations and material on the order. All operations with an equal maximum difference value on the same order are regarded as critical. Critical operations are included in the total number of delayed operations below. Select this alternative in order to only display the critical operations.

Delayed

The value 22 before Delayed shows the total number of operations with a difference between the planned finish period and the new finish period. Critical and Definite delayed operations are also included in this selection. Select this alternative if you want to show all delayed operations.

Not Delayed

The value 139 before Not delayed shows the number of operations without a difference value. Select this alternative to only see these operations.

Overload

The value 9 before Overload, shows the operations for which the work centers have an overload in relation to the master plan the week of the operations' planned finish periods. This check is made only if the setting Against master planClosed By selecting this setting an overload analysis will be made for work centers that are not configured with the setting Reliable new finish. The analysis checks if the work center has an overload the week when the operation will be run. If a work center has an overload against the master plan, the OB and the hours are displayed in red under the Result tab. is checked under the Create tab only for the operations with work centers that have not configured the setting Reliable new finish. Select this alternative to only see these operations.

Definite Delay (Lag)

The value 11 before Definite delay (lag), shows the number of operations with a planned finish period in past time (a so-called lag). Select this alternative to only see these operations. You will see a blue exclamation mark (!) for these operations in the structure list.

No Operations

If you select this alternative, no operations will be shown.