The Info Menu
Under the Info menu you will find several alternatives that are linked to the different bars in the lead time chart. The following alternatives exist for the different bars in the chart:
- Requirement calculation - starts a "Requirement calculation from lead time chart" that calculates all the M-parts in an order as default. This is useful e.g. when analyzing effects and consequences of a replanning.
- Show Info - shows a little dialog box containing additional preparation and order information for the current bar. Here you can also perform replanning by entering another start or finish period.
- Loading / Work Center - (operation) starts the procedure that calculates the loading plan and capacity for the work center that is tied to the operation. Read more about Loading / Work Center in the Help Function for that procedure.
- Material Info - (parts) shows a material list for incorporated material.