Planned Setup Time

Here you can enter a new planned setup time during replanning. Always enter the setup time in hours. When adding, you can also choose to enter a planned setup time. The setup time entered here will be registered as planned in the post-calculation. If you leave this field empty, there will be a post-calculation difference. If you want to create a loading, you must enter a setup time.

Subcontracts show the setup cost in red and in the company currency.

If you modify the planned setup cost for subcontracts in the Planned setup time field, the setup cost will not be recalculated in the Planned setup cost field. If you want to modify the setup cost you should use the Planned setup cost field instead. That filed also shows the setup cost in the currency registered on the operation in the preparation.