You are here: Accounting > Project > Project Activity List > Printout Samples

Printout Samples

The Activity list in this example is classified by the person responsible for the activity. For each activity the list shows to which project the activity belongs, the planned start and end date, planned and reported time, finish date, who performed the activity and status of the activity. By using the Info menu (right-clicking) it is easy to link to a number of procedures.

Sample of a Project Activity List classified by Responsible.

The Activity log classified by Project. At the top you can see general information such as Name, Responsible, Status, Type, Group ans Customer. For each project you can then see Activities, Cost type, who performed the activity, Reference, Amount, Time, Employee number, Work center, Department, and Consecutive number. At the bottom of the list you will see a total per project.